Runbook
Build and rehearse the sequence early.
Every activity has predecessor, owner, duration, evidence and escalation.
Separate configuration, conversion, integrations, security, banking, reporting and jobs.
Expose dependencies on legacy close, audit, banks, vendors and third parties.
Production validation
A successful load is not a successful cutover.
Reconcile converted balances to approved evidence.
Validate production roles, approvals, banking, interfaces, notifications and reports.
Track failed/delayed activities against go/no-go criteria.
Handoff
Make the production decision defensible.
Explicit go/no-go authority and blockers.
Accepted residual risks documented.
Hypercare staffing and first-close ownership confirmed.